GDA Adds 50 MW of New Power Capacity in Texas

GDA expands its total power capacity by nearly 10% with 50 MW deployments across two West Texas sites, enhancing grid support and taping into more clean energy
Houston, TX February 26, 2025 – Genesis Digital Assets Limited (“GDA”), one of the largest bitcoin mining companies in the world in terms of hash rate, announced the energization of an additional 50 MW of mining capacity across its Pyote and Vernon sites in West Texas. This latest expansion includes two 20 MW buildings and a 10 MW container setup featuring cutting-edge mining hardware. The deployment marks a near 10% increase in GDA’s total power capacity, further strengthening its position as a leader in the industry.
GDA is leveraging next-generation mining hardware and infrastructure improvements to maximize efficiency without increasing its physical footprint.
The newly energized capacity will participate in Texas’ demand-response program, contributing to grid stability by adjusting energy consumption in response to peak demand periods. This underscores GDA’s role as a responsible energy consumer and a key player in improving energy security in Texas.
“Bitcoin mining requires the highest levels of efficiency, and GDA continues to adapt and lead that change from out front,” said Abdumalik Mirakhmedov, Executive President of GDA. “This latest deployment gives our Texas operations the efficiency needed to compete at the top without sacrificing responsible energy use. By integrating next-generation mining hardware and participating in demand-response programs, we both enhance our operational capabilities and contribute to a more resilient and balanced energy grid.”
The expansion underscores GDA’s bet on the United States maintaining a leading role in the global Bitcoin mining sector for a long time. Texas is at the forefront due to its favorable regulatory environment, energy infrastructure, and access to renewable power sources.
About GDA

GDA is one of the world’s largest and most experienced industrial-scale Bitcoin mining companies, with a track record of building, managing, and scaling data center operations spanning nearly a decade. We champion innovation, responsible energy use, and investment in the communities where we operate globally, including the 20 data centers across North America, South America, Europe, and Central Asia. With a total power capacity of over 600 MW, the company has brought over 150,000 miners online and was named to Fast Company’s 2024 list of the Next Big Things in Tech in the fintech and blockchain category. At GDA, we are committed to supporting the infrastructure for the future of money by making the Bitcoin network more robust, resilient, and secure.