Pyote Update May 2022

Updates

  • Substation: Three (3) number of transformers totaling to a power capacity of 150MW installed
  • High Voltage Equipment are installed
  • Transmission Line Erected
  • Cable trenches and cable pulling in progress and substation will enter into testing phase for 150MWs
  • Data Center Buildings are in progress with 88MW buildings