- Substation: Three (3) number of transformers totaling to a power capacity of 150MW installed
- High Voltage Equipment are installed
- Transmission Line Erected
- Cable trenches and cable pulling in progress and substation will enter into testing phase for 150MWs
- Data Center Buildings are in progress with 88MW buildings