- Electrical construction is in progress
- Overhead work: all poles are framed and set. All the wire is hung and sagged
- Buildings 1-4: All conduits have been installed, and all transformer pads have been placed
- Buildings 1-2: All transformers have been set and terminated
- All Buildings are fully erected as of November 30, 2022.